Genesis Energy
Duroweld have, over a number of years supplied their services to overlay some of our high wear parts for our pulverized fuel mills. We had been experiencing high wear on our rollers and table. We had spare parts to change out but this took considerable effort and time.
We asked Duroweld to perform a test on one of the mills to ascertain just how good the results would be.
The results of the test were extremely good. They reduced down time of the mill and gave us considerably longer service intervals. We found that if we overlaid the parts before they got into a poor state of repair they also reduced the amount of material we had to apply for optimum protection from wear.
The results were in fact so good that we have considerably reduced the maintenance required on our machinery, allowing for a greater up-time and lower costs - so it was a win/win situation for us at the work face.
“ Duroweld are an extremely professional company to deal with. Practically they fitted into some pretty tight time frames and we found them always professional to work with.”
J Clapp, Huntly Power Station